We are making good progress here. All the bricks has been done. Most of the wiring and the fibre has been installed.
External doors are going into ensure everything is locked up before Christmas break.
I was bit late to blog, but we are making good progress. Frame completed with invoice received for 20%. When I went yesterday they have done most of the roof as well.
I had an appointment with SS on Friday, things are moving along well. Carpenters have started framework,and expected to finish by 23rd. That’s when to expect the next payment.
Also SS mentioned that he is hoping to finish everything by May 2013.
Concrete poured on 9th November.
Expecting the first progress payment from Metricon and first home buyer’s grant from government.
We did a site visit after work today, they have done the prep work for concrete. Great to see the boundaries of the house.
The concrete will be poured on Friday.
Josh gave a call on Friday. The slab will be poured on 7th and frame will be started on 14th. Which is really good. Nice to see things are moving quickly.
When we did the site visit it looked rooms are smaller than we thought, but we will go to display house and try to understand the dimensions.
Finally after 7 months waiting time the site work has started on our new house.
Metricon has started work on 24th October with earth works as promised. To be honest this is the only thing they have done on time. Its an another story. We have been to the site almost everyday now.
24th October: Site start with scrape and leveling
25th October: Some new pegs, seems something has happened. but can’t figure out what!
27th October: We have electricity! Looks like some kind of piers has been installed and poured some concrete.
Our site supervisor Josh hasn’t called us yet, but it’s good to see something happening on the site.